Nordex has secured its first order in New Zealand, with Mercury selecting 40 N133/4.8 turbines for the 192 MW Puke Kapo Hau wind farm on the South Island.
The agreement, announced on 22 October, also includes a comprehensive 30-year service contract, establishing a long-term operating role for the turbine manufacturer in the country.
The project is located in the eastern foothills of the Lammermoor Range in Otago, where average wind speeds exceed eight metres per second. Installation of the first turbine on a 90-metre steel tower is scheduled for early 2028, with the first unit expected to be commissioned in mid-2028.
Nordex plans to work with local contractors on crane services, installation and final commissioning activities as it develops its New Zealand capabilities.
For Mercury, the project extends an established programme of wind development. For Nordex, it creates a new national market alongside its existing Australian business.
The order marks the procurement stage of the development; turbine installation and commissioning remain future milestones.