EnviTec Biogas has reported further construction progress at the Vara biomethane project in Sweden, where initial renewable gas production is scheduled for January 2027.
The plant is being developed for Biogas Västra Skaraborg, an association of approximately 100 farmers. It is designed to process around 370,000 tonnes of agricultural feedstock annually.
EnviTec said on 23 October that the EnviThan gas upgrading system had passed its factory acceptance test and had been installed. Concrete tanks, feedstock handling equipment and heat exchange systems have also reached significant installation milestones.
The facility will convert regional pig and cattle slurry and manure into biogas, then upgrade the gas to the specification required by a downstream customer-supplied liquefaction plant.
Once operational, the project is expected to provide up to 70 GWh of biomethane annually for Bio-LNG production.
Cold commissioning is scheduled for the autumn, followed by a staged biological start-up and coordinated commissioning of the upgrading and liquefaction systems.
The project also incorporates heat recovery from digestate to preheat incoming liquid feedstock.
Illustrative photograph: Julia Koblitz / Unsplash. Not a photograph of the Vara project.